Serving Southern New Hampshire, Middlesex and Essex Counties Massachusetts
Melanie D. of Plymouth, New Hampshire has been living in her new home for about 2 months. She had noticed some sagging on the main floor during the repurchase inspection. She would like to have the floors be level or as level as possible. She decided to call Erickson Foundation Solutions about a free inspection.
Design Specialist Paul Magowan arrived at the home and began inspecting the main floor and basement. Paul noticed that in the basement that the lally columns/ temporary supports aren't supporting the home as well as they once did. Paul recommended installing 5 SmartJacks under the main support beam of the home. He also recommended installing two additional supplemental beams that have two SmartJacks supporting each supplemental beam.
Crew Lead Ed Nadreau and his team arrived at the home and began installing the 9 total SmartJacks and two supplemental beams. The crew was able to level the floors and Melanie was very happy with the results.